Milestones

Tasks 1 and 2 will be completed in the first year, as well as installation of CGPS instruments at 3 SIL stations. Task 3 will be completed in the second year, as well as installation of CGPS instruments at 2 SIL stations. Task 4 be conducted in year 3 and 4, as well as well as upgrading of 5 SIL stations to include CGPS observations.