| Icelandic Meteorological Office
Dept. of Geophysics |
The Icelandic continuous GPS network - ISGPS, March 18, 1999-February 20, 2000
Þóra Árnadóttir, Halldór Geirsson and Bergur H. Bergsson,
Icelandic Meteorological Office
Christof Völksen,
The National Land Survey of Iceland
Date: June 15, 2000
The Icelandic Meteorological Office (IMO) operates a network of continuous
Global Positioning System
stations in Iceland to monitor crustal deformation.
The network is called ISGPS.
Four stations are in the Hengill triple junction area
and two are south of Mýrdalsjökull.
The main purpose of the network is to monitor these two volcanic areas
that have shown signs of unrest with
increased seismicity in the Hengill area
since mid-1994, and Mýrdals- and Eyjafjallajökull
since mid-1999.
The GPS stations were installed during the period from March to
October 1999.
Two more stations are planned near
Eyjafjallajökull, and one in Vestmannaeyjar, in the year 2000.
This report describes the ISGPS network, instrumentation and
some technical details, as well as first results of the data processing,
as of February 20, 2000.
We process the data using the Bernese V4.2 software and calculate
daily station coordinates and uncertainties. From the time series
of daily station coordinates we estimate
east, north and up components of the station velocities.
The time series are still short for most of the stations, so these
velocity estimates are rather uncertain.
The vertical velocity estimate is further downgraded due to
large vertical offsets (up to 22 mm) observed when antenna
radomes were installed.
The largest signal is
at station VOGS, which is moving east relative to REYK at about 70%
of the expected NUVEL-1A velocity of the North American plate relative
to the Eurasian plate.
The station at Ölkelduháls shows no significant horizontal motion
nor subsidence.
The time series at the stations near Mýrdalsjökull are too short, and the
displacements too small to allow meaningful velocity estimates for these
stations.
GPS measurements have been performed to measure
crustal deformation in Iceland since 1986
[Camitz et al. (1995), ,
Foulger(1987),
Hackman et al. (1990),
Heki et al. (1993),
Jahn(1990),
Sigmundsson et al. (1992),,
Sturkell et al. (1994),
Sigmundsson et al. (1995),
Hreinsdóttir et al. (2000).
Network measurements allow good spatial coverage, but rather poor resolution of
temporal variation in deformation rates.
A number of large continuous GPS (CGPS) networks have been initiated during
the last 5 years, the largest to date is in Japan with over
a thousand stations. Several volcanic centers are monitored
with CGPS, for example Kilauea volcano on Hawaii [
Lisowski et al., 1996] and
Long Valley Caldera in east central California [
Dixon et al, 1997].
The advantage of using CGPS in regions where deformation
can be complex both spatially and temporally, is that frequent
measurements can be made with high precision. If the sites are
carefully chosen, a few stations (depending on the complexity of
the system) can give accurate information on the strain accumulation
of the area over a period spanning from hours to years.
The drawback of CGPS is that the instruments are still rather expensive,
and it is not yet possible to monitor
the deformation in real-time with sub-centimeter precision,
in the same way as, for example,
continuous volumetric strain measurements can be used
[Linde et al., 1993].
High precision GPS measurements require use of precise
orbits that are not available until about 2 weeks after the measurements.
Data processing of short sessions, less than 24 hours, also degrades
the precision.
Several research groups are working towards real-time processing
of GPS data, which is particularly useful for volcanic hazard monitoring
[UNAVCO, 1999].
The first CGPS station in Iceland was installed in Reykjavík (REYK)
on November 2, 1995, by a German group at
Bundesamt für Kartographie und Geodäsie (BKG, formerly IFAG).
The station is located on the roof of
a building at the University of
Iceland, and is a part of the International GPS Service (IGS) network.
The same group installed a GPS/GLONASS station, REYZ,
next to REYK
on September 11, 1998. Data from REYZ are not publically available
at present.
The second CGPS station in Iceland was installed by the German
group in Höfn, Hornafjörður (HOFN) on May 27, 1997. This station
is a part of the European Reference Frame (EUREF) network
[EUREF, 2000].
The Icelandic Maritime Administration (IMA) operates 6 coastal stations
for differential
GPS. These stations are L1 only, and located on top
of lighthouses. In addition IMA has a dual frequency station at
its central office in Kópavogur, where the antenna is on a 15 m
high mast.
Seismic activity at the Hengill
triple junction in SW Iceland increased in mid-1994.
Figure 1 shows a map of the Hengill area.
Besides horizontal
shearing, the earthquakes have been
linked to continuing uplift in the Hrómundartindur area,
at a rate of about 2 cm/yr
since 1993 Sigmundsson/etal:1997, Feigl/etal:2000.
The largest earthquake sequence to date started on June 3, 1998,
culminating in a ML=5.1 earthquake on June 4,
followed by an unusually long period of aftershocks, that lasted
for over two weeks Agustsson:1998, ArnadottirHen/etal:1999.
A second earthquake sequence started on November 13, 1998, with a
ML=5.0 earthquake in the Ölfus area, and an aftershock
sequence that lasted 3 days
RognvaldssonEq/etal:1999.
These earthquake sequences and measurements of continuous
uplift caused public concern and
funding to purchase four GPS instruments to use for
continuous measurements was obtained from the Icelandic Government
and the Reykjavík District Heating (now
Reykjavík Energy).
The first continuous GPS station in the ISGPS network
was installed at Vogsósar (VOGS)
and started collecting data on March 18, 1999.
The antenna is placed a few meters from the SIL seismic station VOS
RognvaldssonHen1/etal:1998.
The station in Hveragerði (HVER) started on March 25, 1999,
Hlíðardalsskóli (HLID) on May 21, 1999, and Ölkelduháls (OLKE)
on May 25, 1999
(see Figure 1 for the station locations).
In July 1999 seismicity increased at Mýrdals- and Eyjafjallajökull,
which are two subglacial volcanic centers in South Iceland.
Figure 2 shows a map of the Mýrdalsjökull area.
A small jökulhlaup
occurred in Jökulsá á Sólheimasandi, which flows southwest
from Mýrdalsjökull,
on July 18, 1999 Einarsson:2000.
Katla volcano is located beneath Mýrdalsjökull,
and the latest large eruption was in 1918.
Eyjafjallajökull
last erupted in 1821-1823. These volcanoes are near populated areas,
and their eruptions can generate large jökulhlaups and ash plumes.
Two continuous GPS stations have been installed to monitor these volcanoes,
and two more are planned in the year 2000.
Funding for three GPS instruments
was obtained from the Icelandic Research Council
(RANNÍS) in 1999, to use for network and
semi-continuous measurements.
The station on Sólheimaheiði (SOHO) was installed on September 24, 1999,
and a second station at Láguhvolar (HVOL) became operational on
October 19, 1999 (see Figure 2).
The Department of Geophysics at the Icelandic Meteorological Office (IMO)
operates a system of 37 digital seismometers (the SIL system)
[Stefansson et al., 1993,
Bodvarsson et al.,1996].
In view of the monitoring responsibility of the IMO it was
decided that IMO would install, operate and analyze
data from the CGPS network
in Iceland. The new network is called ISGPS and is shown in
Figure 3.
Table 1 lists the station information.
Station |
Lat. (N) |
Lon. (W) |
Elevation (m) |
Receiver |
Antenna height (m) |
HLID |
63.92110 |
21.38970 |
45.5 |
Trimble 4700 |
0.9089 |
HVER |
64.01715 |
21.18481 |
84.4 |
Trimble 4700 |
0.9843 |
HVOL |
63.52628 |
18.84754 |
199.3 |
Trimble 4000SSI |
1.0443 |
OLKE |
64.06312 |
21.21989 |
484.9 |
Trimble 4700 |
0.9742 |
SOHO |
63.55247 |
19.24665 |
791.6 |
Trimble 4000SSI |
1.0121 |
VOGS |
63.85269 |
21.70365 |
7.6 |
Trimble 4700 |
0.9721 |
REYK |
64.13878 |
21.95548 |
27.6 |
Rouge SNR-8000 |
0.0680 |
|
Table 1:
List of stations, coordinates, elevation above sea level,
instrument type and
vertical antenna heights to the antenna ground plane.
The station elevation measured by GPS is height above the reference
ellipsoid. The height above sea level is calculated by subtracting
the geoid height from the ellipsoidal height. The geoid height
we used was obtained from the National Land Survey of Iceland.
The plan was originally to co-locate the CGPS stations with SIL
seismic stations to minimize operation cost of the network. Each
SIL station is equipped with a PC computer running the UNIX operating
system, and is connected to the IMO through an X.25 link
[Bodvarsson et al., 1999].
Few of the SIL stations are ideally located for monitoring
crustal deformation at volcanic centers in Iceland.
It was therefore
decided to install some of the CGPS stations
at optimal locations for detecting
volcanic deformation, despite more costly operation
than if they were co-located with SIL stations.
The ISGPS network uses
Trimble 4700 and Trimble 4000SSI GPS instruments and Trimble
choke ring antennas.
Both types of
receivers are dual-frequency
systems, i.e., track both L1 and L2 signals. They are
capable of tracking up to 12 satellites simultaneously and record
both P-code and carrier phase data at 15 s intervals.
Each antenna is mounted on a one meter high stainless steel quadripod
that is bolted and cemented into stable bedrock.
A geodetic monument (pin) is also installed to make it possible
to replace the antennas with high accuracy.
Figure 4 shows the instrument installation at station HVOL.
Gray plastic domes (radomes) from the
Southern California Integrated GPS Network (SCIGN) are
used to protect the antennas from snow, ice and possible
vandalism.
At present there is no software available for UNIX or LINUX
that can facilitate remote downloading of data from the Trimble 4700 receivers.
We use the Universal Reference Station (URS)
software from Trimble to control the Trimble 4700 instruments,
collect the raw data and transform the data
into RINEX format [Gurtner,1994].
The URS software runs on a PC under the Windows operating system.
The data are remotely downloaded via modem once every 24 hours
from the IMO.
Figure 5 shows a schematic diagram of the instrument
setup at station HVER.
The setup at the stations running Trimble 4000SSI receivers is somewhat
different.
The data are collected into the internal memory of the
receivers and the UNAVCO software Lapdogs [UNAVCO, 1999]
is used to remotely download the raw data to the IMO once every 24 hours.
The data are then translated into RINEX format at the IMO using the
Bernese software TRRINEXO (before March 2, 2000)
and the UNAVCO software TEQC [UNAVCO, 1999,
Estey and Meertens, 1999].
Figure 6 shows a schematic diagram of the station setup
at HVOL.
The data are available to the general public via the internet
a few hours after they are retrieved from the stations (just after midnight
GMT).
The URL is: http://www.vedur.is/ja/gps.html.
We use data from the International GPS Service (IGS) station in
Reykjavík (REYK) as a reference station for our network.
The station REYK has a Rouge SNR-8000 receiver and a Dorne Margolin choke ring
antenna, and is located on the roof of
a building at the University of
Iceland.
The data from REYK (24 hour RINEX files) are available via
anonymous ftp from igs.ifag.de
a few hours after the measurements are performed.
We will not describe the technical details of the GPS system
in this
report, but refer interested readers to e.g.,
[Leick(1990)] and [Rothacher and Mervart(1996)].
When the data have been downloaded to the IMO they
are processed using the Bernese V4.0 and V4.2 (after January 1, 2000)
software Bernese4.0:1996.
We use precise orbits from the Center for Orbit Determination in Europe (CODE)
which are available by anonymous ftp from ubeclu.unibe.ch,
about 2 weeks after the measurements.
The CODE orbits are in the International Terrestrial
Reference Frame 1997 (ITRF97) [Boucher et
al., 1999],
as of August 1, 1999 (T. Springer, pers. communication, 1999).
The satellites also broadcast orbits which are in the
World Geodetic System 1984 (WGS-84)
reference frame. These orbits are rarely used as they are less
precise than CODE orbits.
The uncertainty in the CODE final orbits is reported as 0.05 m
whereas the uncertainty of the broadcast orbits is 3 m. An
orbital error of 2.5 m causes an error of 0.1 ppm in baseline
estimation, whereas an orbital error of 0.05 m causes 0.002 ppm
error in baseline.
For real-time GPS analysis it is better to use CODE predicted
orbits, which have a reported error of 0.2 m,
than the broadcast orbits [Rothacher and Mervart(1996)].
We use data from the International GPS Service (IGS) station in
Reykjavik (REYK) in our analysis.
Data from REYK are used in the CODE orbit determination, hence our
ISGPS network coordinates are in the ITRF97 reference frame.
We use ITRF97 epoch 1997.0 station coordinates and velocities
to update the coordinates for REYK each week.
We follow the same processing strategy as used for the European
network solution Bernese4.0:1996.
This is a different strategy than used in processing GPS measurements
from network campaigns by the Nordic Volcanological Institute
[Hreinsdottir, 1999].
The main difference is that we use the geometry-free
(L4) linear combination
rather than the wide-lane (L5) combination
(see discussion below).
We estimate station coordinates using 24 hours of
data and a constant 15
elevation angle cut-off,
i.e., data from satellites that are less than 15
above the horizon
are not included in the analysis.
The first several steps follow the routine processing scheme of
the Bernese software. The orbits are converted into
the correct format using the program PRETAB and one standard arc orbit for
each day generated with ORBGEN.
The RINEX data files are translated into Bernese format with the program
RXOBV3. Then three preprocessing programs are used. First, CODSPP computes
the receiver clock error and estimates station coordinates using
zero difference code measurements. In the next step, SNGDIF creates
the phase single difference files between receivers from observations
at the same time. Finally, MAUPRP computes the triple difference residual
for all the observations, corrects big jumps that usually originate
from receiver clocks, and deletes cycle slips.
Now the actual parameter estimation program GPSEST is run to
calculate precise station coordinates. This program is run several times
to obtain the final solution. In the first run the program estimates
station coordinates using the ionosphere-free linear combination (L3),
where the ionospheric path delay is practically eliminated
Bernese4.0:1996.
We use the Saastamoinen model to correct for the signal delay due
to the troposphere at each site [Rothacher and Mervart(1996)].
The improved station coordinates are then
used in the next run of GPSEST where we constrain all the station coordinates
and estimate an ionospheric model using the geometry-free linear combination
(L4) which is independent of receiver clocks and geometry
(i.e., orbits and station
coordinates). It contains the ionospheric delay and the
initial phase ambiguities
[Rothacher and Mervart(1996)].
GPSEST is run for the third time using the
ionospheric model estimated in the previous step. In this run we
constrain the coordinates of REYK, and
estimate and save the L1 and L2 ambiguities.
In the final run of GPSEST the L1 and L2 ambiguities are
introduced, and the L3 linear combination used to calculate
the final station coordinates.
In the final step of GPSEST we calculate the final station coordinates
and full covariance matrix for the daily solutions.
Systematic errors or mismodelled parameters
are not included in the formal error estimate done by GPSEST.
Therefore the uncertainty in the final station coordinates reported by
GPSEST is underestimated.
A more accurate estimate of the error can be obtained
by calculating the average station coordinates for each week
using the Bernese network adjustment program
COMPAR [Rothacher and Mervart(1996)].
COMPAR calculates a network solution from a given set of daily solutions
and the variation of the daily solutions from the network solution.
The variation gives a more realistic estimate of the error in the daily
coordinate solutions than the formal uncertainty calculated by GPSEST.
We find that the errors
in the station coordinates estimated by GPSEST should be scaled
by a factor of 3 to obtain an improved error estimate.
Figure 7 shows histograms for the difference between
weekly network solutions and the daily solutions, after removing outliers
(see below).
The RMS repeatability in the daily coordinates
for the stations is about 3 mm in north and east,
but about 11 mm in vertical.
The large uncertainty in the vertical component
is due to the satellite geometry (all the
signals from satellites come from above ground) and the variable
troposphere and ionosphere delays of the signal that are difficult to
estimate accurately.
To monitor crustal deformation measured by the ISGPS network
we calculate the station motions relative to REYK in
east, north and up, relative to the station coordinates at a reference
epoch.
For example, we calculate the average station coordinates for GPS week 1012
(May 30 - June 5, 1999) using
COMPAR. We then use these average station coordinates as
a reference for the Hengill area, since all the stations there were in operation
by this time.
The station displacements are then calculated relative to
the average station coordinates during GPS week 1012, assuming that REYK
does not move.
From the displacement time series we can calculate the station velocities
for each component (east, north and up)
by fitting a straight line to
the station displacements and their uncertainties
(i.e., calculate the weighted linear least squares solution).
The weighted residual sum squared is,
|
(1) |
where
r is
the residual vector, i.e., the difference between the observed
and predicted data, and
is the data covariance matrix.
In this case we do not consider correlated errors,
so
is a diagonal matrix.
The number of degrees of freedom
for the problem is
where N is the number of data and m is the number of unknowns.
When fitting a straight line to the data, i.e., solving
F(t) = at +b,
where t is time and F(t) is the displacement, we have
two unknowns, a and b.
To test how well the data are fit by the straight line model
we can calculate the value
= .
A
= 1.0 indicates that the model is a good fit to the data
and the error estimates of the data are appropriate.
Before the data can be modelled we need to remove outliers
from the datasets, as they can have a large effect on the model in
a linear least squares problem such as this one.
Outliers are identified as days with
large difference between the daily solution and a weekly network solution,
calculated with COMPAR.
If the difference is larger
than 20 mm in north or east component
or 45 mm in vertical,
we remove all components of data for that
day from the analysis.
Data with uncertainties larger than 5 times the RMS values
for each coordinate are also removed.
Table 2 lists the calculated station velocities
and uncertainties at the 2level, assuming a constant rate for each component of motion.
We find that there are large offsets (up to 22 mm) in the
vertical component, that appear to be caused by
the antenna radome installation. We estimate
the vertical velocity before and after radome installation where
the time series are long enough to yield meaningful estimates.
Apparent offsets in east and north due to radome installation
are not easily detectable for these time series.
We are currently testing the effect of radome installation.
Tests conducted by the USGS, Scripps, and
Jet Propulsion Laboratory (JPL)
indicate that the radome introduces less than 0.2 mm changes
in horizontal phase center and less than 2 mm changes in vertical phase center
[SIGN (1999)].
Table 2:
Calculated velocities of stations in east, north and up, relative
to REYK. N is the number of data, for each component,
used in the calculation, V is the velocity,
and E, N and U subscripts denote east, north and up respectively.
The vertical velocity is estimated before and after radome
installation, VU1, and VU2 respectively, where possible.
The reported uncertainty is at the 2
level.
The velocities are calculated assuming a linear fit
to each component of motion during the whole period.
Outliers are removed (see discussion in text).
Station |
N |
VE (mm/yr) |
VN (mm/yr) |
VU1 (mm/yr) |
VU2 (mm/yr) |
HLID |
166 |
9
2 |
-2
3 |
28
23 |
30
27 |
HVER |
267 |
4
1 |
-5
1 |
|
|
HVOL |
63 |
3
8 |
5
10 |
|
-48
30 |
OLKE |
202 |
1
1 |
2
2 |
|
0
5 |
SOHO |
78 |
10
4 |
5
6 |
|
-5
36 |
VOGS |
263 |
12
1 |
-2
1 |
1
8 |
0
13 |
|
We limit our analysis to data collected before
February 20, 2000,
which is day number 51, and the beginning of GPS week 1050.
The results
are discussed in the following sections.
Figure 8 shows the horizontal and vertical motion of
VOGS relative to REYK as a function of time, and the estimated
1
uncertainty of each measurement.
We have estimated the velocity of VOGS relative to REYK
by fitting a straight line through each component of the calculated
displacements (see discussion above) after removing 12 outliers
(days 90, 120, 182, 243, 244, 271, 289, 311,
320, 323, 393 and 403).
The best fit line gives rates of motion towards east of
about 12
1 mm/yr and
= 1.7.
The velocity in the south direction is 2
1 mm/yr,
with
= 1.5 for the estimate.
VOGS appears to be uplifting at a rate of
1
8 mm/yr (
= 0.7), before day 328, and
a rate of 0
13 mm/yr after that (
= 0.7).
The installation of the radome appears to cause a 20 mm vertical
offset in the time series.
The change in the estimated velocity before and after radome
installation is insignificant.
A longer time series, without changes in the radome, will yield a
better estimate of the long-term vertical rate.
The best fit lines are shown as heavy black lines on
Figure 8.
The east and north components of velocity
translate to a motion of 12.2
1 mm/yr
in direction N99E 1.
The NUVEL-1A plate motion of the Eurasian
plate relative to the
North American plate is
18.5 mm/yr in direction N103E
[DeMets et al., 1990;
DeMets et al., 1994].
If we assume that VOGS is on the Eurasian plate and REYK is on
the North American plate,
VOGS appears to be moving at about 70% of the full
NUVEL-1A plate velocity relative to REYK.
We calculate the velocity of HVER relative to REYK for the
period shown in Figure 9.
We delete
17 outliers (days 182, 201, 244, 270, 283,
311, 315, 317, 320, 322, 323, 325, 337, 346,
393, 403 and 408).
Assuming that each component of motion can be fit by a single straight line
gives a velocity of 4
1 mm/yr towards east (
= 2.0) and
5
1 mm/yr southward motion (
= 2.6).
We do not estimate the vertical component of motion because the time series
are too short between changes in the radome.
There appear to be short period temporal variations in the vertical
signal.
It is possible that they are due to
atmospheric or ionospheric effects that we are not modelling, or
local changes influenced by the geothermal system in Hveragerði.
Figure 10 shows the relative motion of
HLID as a function of time.
We have estimated the velocity of HLID relative to REYK using
data before day 342, 1999. Data after day 341 is not reliable because
the antenna at HLID was covered
in snow several times after that date.
We deleted 19 outliers (days 175, 182, 235, 236, 237, 244, 256, 275,
285, 287, 290, 291, 296, 300, 311, 314, 320, 323, and 325).
The best fit line gives velocities of 9
2 mm/yr towards east
(
= 1.5) and
2
3 mm/yr towards south (
= 2.5).
We estimate the vertical velocity before and after radome installation
(day 235).
Before day 235 the vertical rate of uplift is 28
23 mm/yr (
= 0.7)
and 30
27 mm/yr (
= 0.8) after day 235.
These rates are similar, but
barely significant at the 2
level.
We estimate a vertical shift of about 22 mm on day 235, when the antenna
radome was installed. This is the largest effect of
radome installation we observe in our network.
The effect of snow covering the antenna is apparent as spurious north,
east and vertical motion after day 341, 1999, on Figure 10.
It is interesting to note that the effect of snow is visible in all
the components, not just the vertical. This may be caused by
asymmetry in the snow cover over the antenna.
Data from the GPS station CASA in Long Valley, that was temporarily covered
with snow, showed only vertical changes
[ Webb et al, 1995].
They report a snow thickness of 1-2 m before loss of signal, causing
up to almost 40 cm apparent positive vertical motion.
On January 14, 2000, we find a positive vertical motion of 21 cm, and 2 cm
in eastward and 4 cm southward apparent motion due to snow cover.
No measurements of snow thickness or estimates of the
geometry of the
snow pile were made at HLID.
The data from HLID should not be used after day 341,
and will not be distributed on the web.
The measurements at this station have been discontinued
(as of day number 75, 2000)
and the antenna will be moved to a better location.
Figure 11 shows the relative motion of
OLKE in east, north and up as a function of time.
Data gaps are due to power failures at OLKE which is a remote station
powered by a windmill.
Data is continually sent to a computer located on Háhryggur,
about 7 km NW of the station.
Some loss of data, causing short sessions from days 240-325, 1999, was
due to partial blocking
of the data transmitter antenna (spread spectrum modem) relative to
Háhryggur.
We estimate the velocity of OLKE relative to REYK by fitting a straight
line to the individual components of motion. First we delete
23 outliers (days 182, 235, 236, 240, 243, 252, 255, 257, 275, 277, 285,
287, 311, 312, 314, 315, 317, 320, 323, 325, 403, 408 and 410).
The velocity we estimate in east direction is 1
1 mm/yr
(
= 2.5),
2
2 mm/yr in north (
= 3.5)
and a vertical rate of 0
5 mm/yr (
= 1.0) after
day 182, when the antenna radome was installed.
The time series before day 182 was
too short to allow a meaningful estimate of the vertical velocity.
The time series from SOHO and HVOL are short and there are several
data gaps due to power failures.
The antenna tribrack was replaced on SOHO on day 313, 1999, causing an increase
in antenna height of 1.3 mm. This antenna height change is included
in the data analysis. SOHO and HVOL are the only stations in the network
with antenna tribracks for leveling and centering the antennas.
Figure 12 shows the relative motion of
SOHO compared to REYK
as a function of time. The average station coordinates for GPS week
1029 (September 26 - October 3, 1999) are used as a reference in the
calculation.
We find the best fit line through the data after removing 13 outliers
(days 274, 289, 290, 315, 317, 320, 323, 325, 384, 387, 393,
403 and 408). The velocities we calculate for the station
are 10
4 mm/yr in east (
= 1.2) and
5
6 mm/yr
in north (
= 2.6). We find a subsidence rate of 5
36 mm/yr
(
= 0.9) after day 311.
The time series before day 311 is to short to allow an estimate of
the vertical velocity.
Figure 13 shows the same as Figure 12
for HVOL.
The average station coordinates for GPS week
1033 (October 24-31, 1999) are used as a reference in the
calculation.
We calculate the velocity of HVOL relative to REYK,
after removing 11 outliers (days 292, 294, 300, 320, 325, 362, 365,
376, 393, 403 and 408).
Assuming a constant velocity we find eastward motion of 3
8 mm/yr
(
= 1.0),
northward of 5
10 mm/yr (
=1.9)
and subsidence of 48 30 mm/yr (
= 0.6).
The antenna radome was installed at the same time as the antenna.
We have also processed the data from our network
using the GIPSY/OASIS software [Webb and Zumberge, 1993].
While the Bernese software is based on parameter elimination
using the double difference technique,
GIPSY/OASIS processes undifferenced observation.
Therefore, common parameters such as the clock parameters of the GPS satellites
and receivers have to be estimated in GIPSY/OASIS,
which are eliminated by the double difference
technique used by the Bernese software.
In principle, however, these two methods give the same results. GIPSY/OASIS
offers one special processing strategy which is called precise point
positioning [Zumberge et al., 1997].
We use precise satellite clock and orbit information supplied by JPL,
and do not estimate these parameters in our analysis.
Precise point positioning is thus possible using data
from only one station.
The main advantage of this procedure
is the reduction of computer time, since the system of normal equations is
fairly small, because the size of the normal equation system grows as the square
of the number of stations.
The processing of data
from a single station using the point positioning method,
takes less than two minutes on a HP-UX K 360 workstation.
A month of data from approximately 20 stations can therefore be processed
in a few hours.
Another advantage of the precise point positioning method is that it
allows one to estimate absolute station
coordinates in the ITRF97 reference system
without using data from fiducial stations.
GPS data from 21 stations covering the margin of the North Atlantic and the
permanent stations in Iceland were processed using GIPSY/OASIS.
Instead of fixing ambiguities, only
float solutions using the L3 combination are computed, which are equivalent
to fixed solutions when the observation window is longer than 8-12 hours
Mervart:1995.
An elevation cut-off angle of 10
and the Niell mapping function
[Niell, 1993 ]
were used for the estimation of
tropospheric parameters.
GIPSY/OASIS was also used to estimate absolute station velocities from
the daily coordinate solutions,
using the full covariance information.
The variances of the individual
solutions are underestimated
in GIPSY.
A more realistic estimation of the variance for the final
coordinate and velocity estimation was obtained by scaling
them by a factor of 2.7.
Figure 14
shows the east, north and up components of the absolute
motion of REYK in the ITRF97 as a function of time.
Outliers with large standard deviations or large offsets from the sample mean
were removed. The largest component of motion of REYK is towards north.
error bars.
1!figures/REYK.ps
|
The estimated absolute velocities of the IGS stations in the ITRF97,
and the 2
errors
are given in Table 3 and Figure 15.
Table 3:
Absolute velocities in the ITRF97,
using results from GIPSY analysis
of data collected before March 1, 2000.
The station velocities, V, are in east (E), north (N) and up (U).
The reported uncertainty is at the 2
level.
Station |
VE (mm/yr) |
VN (mm/yr) |
VU (mm/yr) |
ALGO |
-15
2 |
2
1 |
-1
5 |
HERS |
16
2 |
10
2 |
-7
5 |
KELY |
-18
4 |
11
3 |
1
8 |
KIRU |
7
3 |
18
2 |
38
7 |
KOSG |
14
2 |
16
1 |
-1
4 |
NYA1 |
6
2 |
15
2 |
7
7 |
NYAL |
12
2 |
16
2 |
16
8 |
ONSA |
13
2 |
14
1 |
0
5 |
STJO |
-11
2 |
12
1 |
-9
4 |
THU1 |
-17
2 |
-2
2 |
-1
7 |
WTZR |
20
2 |
14
1 |
-2
5 |
TROM |
15
3 |
15
3 |
23
9 |
HOFN |
15
3 |
9
2 |
6
7 |
REYK |
-11
2 |
19
2 |
-8
5 |
REYZ |
-5
5 |
25
4 |
-2
12 |
|
For comparison, Figure 15 also shows the
expected station velocities calculated from the
NNR-NUVEL-1A model (red arrows)
[Argus and Gordan, 1991].
The agreement with the model is fairly good,
except at the station pairs in Ny Alesund (NYAL/NYA1) and
Reykjavík (REYK/REYZ).
These locations have two antennas operated
within a few meters of each other. The antennas in Reykjavík are about
1 m apart, and about 8 m in Ny Alesund.
The differences in velocities are probably due to the short time series.
Data from the station REYK were processed for the period between
March 1999 and February 2000, whereas data for the station REYZ
were only available after July 19, 1999.
In general most velocities are statistically
significant at the 2
level.
The motion of the ISGPS stations relative to
REYK are given in Table 4.
Table 4:
Calculated velocities using results from GIPSY analysis
of data collected before March 1, 2000.
The station velocities, V, are in east (E), north (N) and up (U),
relative to REYK.
The reported uncertainty is at the 2
level.
The velocities are calculated assuming a linear fit
to each component of motion during the whole period.
Effects due to radome installation are not considered.
Station |
VE (mm/yr) |
VN (mm/yr) |
VU (mm/yr) |
HLID |
1
5 |
-11
4 |
-27
13 |
HVER |
7
3 |
-6
2 |
-10
7 |
HVOL |
3
15 |
13
11 |
-29
36 |
OLKE |
2
4 |
-1
3 |
9
9 |
SOHO |
25
8 |
3
6 |
-36
20 |
VOGS |
13
3 |
-4
3 |
-13
8 |
REYZ |
6
5 |
6
4 |
6
13 |
|
The motion between REYK and REYZ is statistically
significant even though both markers are mounted in the same
concrete construction.
Therefore, the velocities from these rather short time series do not seem to
be entirely reliable.
It is worthwhile to note that the 2
errors in the estimates of
relative motion
(Table 4) are larger
than for the absolute motion (Table 3). The reason is
that there are no correlations between coordinates of different stations,
since the stations are processed individually in the point positioning scheme.
This, in turn, causes the errors of relative velocity estimations from the
point positions to be larger than errors for the relative positioning
(Table 2).
Comparing Table 2 and Table 4,
we see that the station velocities agree
at the 2
level,
for all but a few components.
Note that possible effects of radome installation were not
considered when estimating the the vertical
velocities in Table 4.
Longer time series will provide more robust velocity estimates
from both analysis methods and a better basis for comparison.
Figure 16 shows the velocities of the stations
in the Hengill area relative to REYK, estimated from the Bernese analysis.
The horizontal velocities are shown with blue arrows.
The error ellipses show the 2
confidence limits. The vertical
velocities are shown with green arrows, and the uncertainties with
red bars.
We see that all the stations in
the Hengill area are moving east relative to REYK. The
eastward velocity increases from OLKE to VOGS.
The east and north components of velocity at VOGS
translate to a motion of 12.2
1 mm/yr in direction
N99E 5.
The NUVEL-1A plate motion of the Eurasian plate relative to the
North American plate is
18.5 mm/yr in direction N104E for Vogsósar (shown with a purple arrow
on Figure 16).
The station VOGS appears to be moving at about 70% of the full
NUVEL-1A plate velocity relative to REYK.
The direction of motion agrees with the
direction of relative plate motion of the Eurasian plate,
assuming that the North American plate is fixed.
This suggests that
the signal observed at VOGS is primarily showing the relative
plate motion between the North American
and the Eurasian plates, and that VOGS is within the plate boundary zone,
hence not moving at the full spreading rate.
The southward motion is largest at HVER (5
1 mm/yr) but
barely significant at the other stations.
OLKE is closest to Hrómundartindur, and appears to be moving vertically
at a rate of 0
5 mm/yr, which is a considerably lower
rate of deformation than estimated for the period 1993-1998.
A longer uninterrupted time series is needed to more accurately
determine the long-term vertical rate.
An uplift rate of about 20 mm/yr
is estimated for the Hrómundartindur area
from various geodetic data from 1993 to 1998
[Sigmundsson et al., 1997,
Feigl et al., 2000 ].
GPS network measurements were done in the Hengill area in
August and November 1998, and
March 1999. The uplift at station RKOT, which is between OLKE and HVER,
was significant during the period from August to November 1998, but
not significant from November 1998 to March 1999
[Hreinsdottir:1999].
Network GPS measurements in the Hengill area done by the National Energy
Authority (NEA)
[Thorbergsson, 1999]
in June 1998 and June 1999, indicate
uplift of almost 3 cm at the station closest to OLKE (7393), relative to
station HH45, which is about 10 km NW of Ölkelduháls.
We plan to re-analyze the data collected by the NEA using REYK as a
reference, to determine if this uplift rate is influenced by motions of
HH45.
A dimensionless number termed ``strain release'', calculated by
105+ML
[Bodvarsson_etal:1996],
is useful to estimate
seismic deformation.
The seismic strain release for the Hengill area is
about 61010 for the year 1998, and about
4109for 1999, using all earthquakes with ML larger than 1.0.
It is therefore clear that the seismic rate of deformation during
1998 is an order of magnitude larger than for 1999.
It is possible that the large earthquake sequence of 1998 changed
the dynamics of the system and we are entering a period of
lower rates of deformation.
A swarm of earthquakes occurred about 2-4 km east of Ölkelduháls on May 25,
1999 (day 145), on the day that the station OLKE was installed.
Four of the earthquakes recorded had ML in the
range of 3.0-3.9. It is possible that some aseismic motion continued
in the area following the swarm, that might affect the rate of
deformation at OLKE.
In any case it is likely that the rates of deformation
are highly variable, changing significantly over
a period of a few months. Longer GPS time series are needed to test
this hypothesis.
Synthetic Radar Aperture (SAR)
measurements in the Hengill area could provide independent
information on the absolute vertical motion during 1999, although
the resolution of temporal variation will not be as detailed as
can be obtained with CGPS measurements.
Figure 17 shows the velocities of the stations
south of Mýrdalsjökull relative to REYK from the Bernese analysis.
The horizontal velocities are shown with blue arrows and
2
error ellipses.
The vertical
velocities are shown with green arrows, and the uncertainties with
red bars.
For comparison we show the calculated NUVEL-1A plate motion relative to REYK,
which is 18.6 mm/yr (purple arrow),
assuming that the stations are on the Eurasian plate.
Longer time series are needed before we can
determine what part of the signal at the stations is due to
plate motions and what is caused by local volcanic sources.
The time series at SOHO and HVOL are still short and there are
many gaps in the data. As with the other stations, there
are large uncertainties in the vertical velocity estimates.
It is therefore not yet clear whether the apparent rate of subsidence
at HVOL is real,
which could indicate that the magma system beneath Katla is deflating.
The eastward motion of SOHO is the only
component of motion that is (barely) significant
at the 2
level.
HVOL does not show any significant horizontal motion during the time period
we analyzed.
This is in agreement with GPS network measurements in the area
for the period August to November 1999 that show little motion
at stations east of Eyjafjallajökull
[Sturkell et al, 2000].
Theoretical models have been
used to calculate surface deformation in the area around Katla
and Eyjafjallajökull [Agustsson:2000]
An ellipsoidal source at the center of the Katla caldera
(63.65N, 19.10W)
with a centroid depth of 4 km and
a volume increase of 0.1 km3would cause about 5 cm in eastward,
8 cm in southward and 3 cm upward motion at SOHO.
The station at HVOL would detect
4 cm westward, 4 cm southward and 1 cm of uplift, for the same
source model.
If the source was centered at 4 km depth beneath the Eyjafjallajökull caldera
(63.63N, 19.63W)
it would cause an eastward motion of 4 cm at SOHO and 1 cm at HVOL,
about 2 cm southward motion at SOHO, and less than 1 cm at HVOL.
The vertical motion would not be significant at these stations.
A spherical source at 7.5 km depth, under either caldera,
would produce slightly larger signals at both stations
(K. Ágústsson, pers. communication, 2000).
Little is known about dike intrusions
under these volcanoes,
and therefore difficult to estimate reasonable source parameters
for such events and how well they would be detected at SOHO and HVOL.
The inherent problem in monitoring crustal deformation due
to magma movements beneath Katla and/or Eyjafjallajökull
is that the volcanoes are covered by glaciers, and the closest
stations are far away from the caldera centers, where the largest
deformation is expected.
It is therefore possible that
magma accumulation of up to 0.1 km3 could occur
at shallow depth beneath Katla or Eyjafjallajökull
without being detected at SOHO and/or HVOL.
This report discusses the first results of the continuous GPS network
(ISGPS) in Iceland. The first station was installed in mid-March 1999,
and we analyze the data up to February 20, 2000.
We estimate station velocities relative to the CGPS station in
Reykjavík (REYK),
by fitting a straight line to each
component of motion.
The main conclusions can be summarized as:
-
- Station VOGS appears to be moving at about 70% of
the NUVEL-1A plate velocity, relative to REYK.
-
- Very little motion is observed at station OLKE, indicating
that the large rates of deformation observed near Hrómundartindur
from 1993 to mid-1998, have decreased since mid-1999.
-
- The short time series and large noise in the vertical component
cause the velocity estimates to be quite
uncertain, particularly for the vertical component.
-
- We detect large vertical offsets (about 21-22 mm)
due to radome installation.
-
- Insignificant motion is detected at SOHO and HVOL, indicating
that magma accumulation at shallow depth beneath Katla during the observation
period is less than 0.1 km3.
Future plans include:
-
- Install two new CGPS stations near Eyjafjallajökull to
improve monitoring of deformation due to possible magma movements
or accumulation beneath the volcano.
-
- Determine the effects of radome installation
in our network.
-
- Use predicted orbits in our analysis for
near real-time data processing.
-
- Improve network solutions and velocity estimates with longer
time series and more sophisticated software.
This project was initiated as a collaboration between the Icelandic Meteorological
Office (IMO), the Nordic Volcanological
Institute (NVI) and the Science Institute at the University of Iceland (SIUI).
Ragnar Stefánsson (IMO), Freysteinn Sigmundsson (NVI) and
Páll Einarsson (SIUI) were instrumental in getting the project
started.
We would like to thank the Icelandic Government, the Reykjavík
District Heating, and the Icelandic Research Council
(RANNÍS) for funding the purchase of the GPS instruments for the ISGPS network.
We thank everyone who has helped with the installation of the instruments,
in particular Halldór Ólafsson and Erik Sturkell at NVI, Haukur Brynjólfsson
at SIUI, and Pálmi Erlendsson, Kristín Jónsdóttir and Jósef Hólmjárn at IMO.
We are grateful for the interest and support we have received from the
local community, and those who have allowed us to set up the instruments
on their property.
We are also grateful for the software
support and help from UNAVCO and the group at BKG.
Sigurjón Jónsson (Stanford, USA),
Klaus Röttcher and Uwe Hessels (BKG, Germany), Mike Jackson,
Lou Estey, Karl Feaux and John Braun (UNAVCO, USA),
John Beavan (GNS, New Zealand),
Susan Owen (USC, USA), Ken Hudnut (SCIGN, USA), Mike Lisowski (HVO, USA),
and Elliot Endo (USGS, USA) were ready to answer a million questions about CGPS.
The figures in this report were generated using the public domain
GMT software
[Wessel and Smith, 1991].
Gunnar B. Guðmundsson provided scripts for the maps shown in this report.
Suggestions from Páll Einarsson, Freysteinn Sigmundsson
Kristján Ágústsson and Barði Þorkelsson helped to improve this report.
Financial support for this project was provided in part
by the EC project PRENLAB-2 (contract number ENV4-CT97-0536) and
the Icelandic Research Council (RANNÍS), grants 981050098 and
981050099 (Þóra Árnadóttir).
Argus and Gordon(1991)
Argus, D.F. and R.G. Gordon 1991.
No-net-rotation model of current plate velocities incorporating plate
motion model NUVEL-1.
Geophys. Res. Lett. 18, 2038-2042.
Ágústsson(1998)
Ágústsson, K. 1998.
Earthquake swarm on Hellisheiði and Hengill in May-July 1998
(Jarð- skjálftahrina á Hellisheiði og í Hengli í maí-júlí 1998).
Greinargerð Veðurstofu Íslands VÍ-G98040-JA06. Report, Icelandic Meteorological Office, Reykjavík
(in Icelandic).
Ágústsson(2000)
Ágústsson, K. 2000.
Katla and Eyjafjallajökull - a few models and thoughts (Katla og
Eyja- fjallajökull - nokkur líkön og hugleiðingar).
Greinargerð Veðurstofu Íslands VÍ-G00002-JA01. Report, Icelandic Meteorological Office, Reykjavík
(in Icelandic).
Árnadóttir,
Rögnvaldsson, Ágústsson, Stefánsson, Hreinsdóttir, Vogfjörð and
Thorbergsson
Árnadóttir, Þ., S.Th. Rögnvaldsson, K. Ágústsson, R. Stefánsson,
S. Hreinsdóttir, K.S. Vogfjörð and G. Þorbergsson 1999.
Seismic swarms and surface deformation in the Hengill area, SW
Iceland.
Seismol. Res. Lett. 70, 269.
Boucher, Altamimi and Sillard
Boucher, C., Z. Altamimi and P. Sillard 1999.
The 1997 International Terrestrial Reference Frame (ITRF97).
IERS Technical Note 27. Observatoire de Paris, France.
Böðvarsson, Rögnvaldsson, Jakobsdóttir,
Slunga and Stefánsson
Böðvarsson, R., S.Th. Rögnvaldsson, S.S. Jakobsdóttir,
R. Slunga and R. Stefánsson 1996.
The SIL data acquisition and monitoring system.
Seismol. Res. Lett. 67, 35-46.
Böðvarsson, Rögnvaldsson, Slunga and
Kjartansson
Böðvarsson, R., S.Th. Rögnvaldsson, R. Slunga and
E. Kjartansson 1999.
The SIL data acquisition system -- at present and
beyond year 2000.
Phys. Earth Planet. Inter. 113, 89-101.
Camitz, Sigmundsson, Foulger, Jahn, Völksen and
Einarsson
Camitz, J., F. Sigmundsson, G. Foulger, C.-H. Jahn, C. Völksen and P. Einarsson
1995.
Plate boundary deformation and continuing deflation of the Askja
volcano, North Iceland, determined with GPS, 1987-1993.
Bull. Volcanol. 57, 136-145.
DeMets, Gordon, Argus and Stein
DeMets, C., R.G. Gordon, D.F. Argus and S. Stein 1990.
Current plate motions.
Geophys. J. Int. 101, 425-478.
DeMets, Gordon, Argus and Stein
DeMets, C., R.G. Gordon, D.F. Argus and S. Stein 1994.
Effect of recent revisions to the geomagnetic reversal time scale on
estimates of current plate motions.
Geophys. Res. Lett. 21, 2191-2194.
Dixon, Mao, Bursik, Heflin, Langbein, Stein and
Webb
Dixon, T.H., A. Mao, M. Bursik, M. Heflin, J. Langbein, R. Stein and F. Webb
1997.
Continuous monitoring of surface deformation at Long Valley
caldera, California, with GPS.
J. Geophys. Res. 102, 12017-12034.
Einarsson(2000)
Einarsson, P. 2000.
Events related to a flood in Jökulsá á Sólheimasandi in July
1999 (Atburðarás í tengslum við hlaup í Jökulsá á Sólheimasandi í júlí
1999).
In: Abstracts from the February meeting of the
Geoscience Society of Iceland, Reykjavík, February 17, 2000
(in Icelandic).
Einarsson and Sæmundsson(1987)
Einarsson, P. and K. Sæmundsson 1987.
Earthquake epicenters 1982-1985 and volcanic systems in Iceland.
In: Þorsteinn I. Sigfússon (editor), Í hlutarins eðli.
Map accompanying festschrift for
Þorbjörn Sigurgeirsson.
Menningarsjóður, Reykjavík.
Erlendsson(1996)
Erlendsson, P. 1996.
Mapping of earthquake fractures east of Brennisteinsfjöll
(Kortlagning jarðskjálftasprungna austan Brennisteinsfjalla).
B.S. thesis, University of Iceland, Reykjavík
(in Icelandic).
Estey and Meertens(1999)
Estey, L. and C. Meertens 1999.
TEQC: The multipurpose toolkit for GPS/GLONASS data.
GPS Solutions 3, 44-49.
EUREF(2000)
EUREF 2000.
The permanent European Reference Frame (EUREF) network.
URL: http://homepage.oma.be/euref/eurefhome.html.
Last modified April 19.
Feigl, Gasperi, Sigmundsson and
Rigo
Feigl, K.L., J. Gasperi, F. Sigmundsson and A. Rigo 2000.
Crustal deformation near Hengill volcano, Iceland, 1993-1998:
coupling between magmatic activity and faulting inferred from elastic modeling of
satellite radar interferograms.
J. Geophys. Res., submitted.
Foulger(1987)
Foulger, G. 1987.
A GPS geodetic survey of the northern volcanic zone of Iceland
1987.
EOS, Trans. Am. Geophys. Un. 68, 1236.
Foulger, Bilham, Morgan and
Einarsson
Foulger, G., R. Bilham, W.J. Morgan and P. Einarsson 1987.
The Iceland GPS geodetic field campaign 1986.
EOS, Trans. Am. Geophys. Un. 68, 1809.
Gurtner(1994)
Gurtner, W. 1994.
RINEX: the Receiver-Independent Exchange Format.
GPS World, July, 48-52.
Hackman, King and Bilham
Hackman, M.C., G.C.P. King and R. Bilham 1990.
The mechanism of the South Iceland seismic zone.
J. Geophys. Res. 95, 339-351.
Hamburger, Meertens, Owen, Dixon and
Stein
Hamburger, M., C. Meertens, S. Owen, T. Dixon and S. Stein 1999.
Meeting report: UNAVCO volcano geodesy workshop.
URL: http://www.unavco.ucar.edu/science_tech/volcano/-
meetings/sep_99.html.
Last modified October 23.
Heki, Foulger, Julian and Jahn
Heki, K., G. Foulger, B. Julian and C.-H. Jahn 1993.
Plate dynamics near divergent plate boundaries: Geophysical
implications of post-rifting crustal deformation in NE Iceland.
J. Geophys. Res. 98, 14279-14297.
Hreinsdóttir(1999)
Hreinsdóttir, S. 1999.
GPS geodetic measurements on the Reykjanes Peninsula,
SW Iceland: crustal deformation from 1993 to 1998.
M.S. thesis, University of Iceland, Reykjavík.
Hreinsdóttir, Einarsson and
Sigmundsson
Hreinsdóttir, S., P. Einarsson and F. Sigmundsson 2000.
Crustal deformation at the oblique spreading Reykjanes peninsula,
SW Iceland: GPS measurements from 1993 to 1998.
J. Geophys. Res., submitted.
Jahn(1990)
Jahn, C.-H. 1990.
A highly precise GPS-epoch measurement in the northeast volcanic
zone of Iceland.
In: J.P. Paquet, J. Flick and B. Ducarme (editors),
Cahiers du Centre Européen de Géodynamique et de
Sismologie.
Luxembourg, 292-304.
Leick(1990)
Leick, A. 1990.
GPS satellite surveying.
John Wiley & Sons, New York.
Linde, Ágústsson, Sacks and
Stefánsson
Linde, A.T., K. Ágústsson, I.S. Sacks and R. Stefánsson 1993.
Mechanism of the 1991 eruption of Hekla from continuous borehole
strain monitoring.
Nature 365, 737-740.
Lisowski, Owen and Segall
Lisowski, M., S. Owen and P. Segall 1996.
The Kiluea Volcano Hawaii, continuous GPS network: recent
results.
EOS, Trans. Am. Geophys. Un. 77, 808.
Mervart(1995)
Mervart, L. 1995.
Ambiguity resolution technique in geodetic and geodynamic
applications of the Global Positioning System. Ph.D. thesis.
Geodätisch-geophysikalische Arbeiten in der Schweiz, report nr. 53.
Niell(1993)
Niell, A. 1993.
A new approach for the hydrostatic mapping function.
In: Proceedings of the International Workshop for Reference Frame
Establishment and Technical Development in Space Geodesy. Tokyo, Japan.
Rothacher and Mervart(1996)
Rothacher, M. and L. Mervart 1996.
Bernese GPS software version 4.0.
Astronomical Institute, University of Berne, Berne, Switzerland.
Rögnvaldsson, Ágústsson,
Bergsson and Björnsson
Rögnvaldsson, S.Th., K. Ágústsson, B.H. Bergsson and
G. Björnsson 1998a.
Seismic network near Reykjavík - network discription and first
results
(Jarðskjálftamælanet í nágrenni Reykjavíkur - lýsing á mælaneti og
fyrstu niðurstöður).
Rit Veðurstofu Íslands VÍ-R98001-JA01.
Research report, Icelandic Meteorological Office, Reykjavík.
Rögnvaldsson, Árnadóttir,
Ágústsson, Skaftadóttir, Guðmundsson, Björnsson, Vogfjörð, Stefánsson,
Böðvarsson, Slunga, Jakobsdóttir, Þorbjarnardóttir, Erlendsson, Bergsson,
Ragnarsson, Halldórsson, Þorkelsson and
Ásgeirsdóttir
Rögnvaldsson, S.Th., Þ. Árnadóttir, K. Ágústsson, Þ. Skaftadóttir, G.B. Guðmundsson,
G. Björnsson, K.S. Vogfjörð, R. Stefánsson, R. Böðvarsson, R. Slunga,
S.S. Jakobs- dóttir, B. Þorbjarnardóttir, P. Erlendsson, B.H. Bergsson,
S. Ragnarsson, P. Halldórsson, B. Þorkelsson and M. Ásgeirsdóttir
1998b.
An earthquake swarm in Ölfus in November 1998
(Skjálftahrina í
Ölfusi í nóvember 1998).
Greinargerð Veðurstofu Íslands VÍ-G98046-JA09. Report, Icelandic Meteorological Office, Reykjavík
(in Icelandic).
SCIGN(1999)
SCIGN 1999.
SCIGN radome project.
URL: http://www-socal.wr.usgs.gov/scign/group/dome.
Last modified March 31.
Sigmundsson, Einarsson and
Bilham
Sigmundsson, F., P. Einarsson and R. Bilham 1993.
Magma chamber deflation recorded by the Global Positioning
System: the Hekla 1991 eruption.
Geophys. Res. Lett. 19, 1483-1486.
Sigmundsson, Einarsson, Bilham and
Sturkell
Sigmundsson, F., P. Einarsson, R. Bilham and E. Sturkell 1995.
Rift-transform kinematics in South Iceland: deformation from
Global Positioning System measurements, 1986 to 1992.
J. Geophys. Res. 100, 6235-6248.
Sigmundsson, Einarsson, Rögnvaldsson, Foulger,
Hodkinson and Thorbergsson
Sigmundsson, F., P. Einarsson, S.Th. Rögnvaldsson, G. Foulger,
K. Hodkinson and G. Þorbergsson 1997.
1994-1995 seismicity and deformation at the Hengill triple
junction, Iceland: triggering of earthquakes by an inflating magma
chamber in a zone of horizontal shear stress.
J. Geophys. Res. 102, 15151-15161.
Stefánsson, Böðvarsson, Slunga, Einarsson,
Jakobsdóttir, Bungum, Gregersen, Havskov, Hjelme and
Korhonen
Stefánsson, R., R. Böðvarsson, R. Slunga, P. Einarsson, S.S. Jakobsdóttir,
H. Bungum, S. Gregersen, J. Havskov, J. Hjelme and H. Korhonen 1993.
Earthquake prediction research in the South Iceland seismic
zone and the SIL project.
Bull. Seism. Soc. Am. 83, 696-716.
Sturkell, Sigmundsson and
Einarsson
Sturkell, E., F. Sigmundsson and P. Einarsson 1994.
Strain accumulation 1986-1992 across the Reykjanes peninsula
plate boundary, Iceland, determined from GPS measurements.
Geophys. Res. Lett. 21, 125-128.
Sturkell, Einarsson and
Sigmundsson
Sturkell, E., P. Einarsson and F. Sigmundsson 2000.
Crustal deformation around Mýrdalsjökull and Eyjafjallajökull,
1967-2000.
In: Abstracts from the February meeting of the
Geoscience Society of Iceland, Reykjavík, February 17, 2000.
Sæmundsson(1995)
Sæmundsson, K. 1995.
Hengill, geological map (bedrock) 1:50000.
UNAVCO(1999)
UNAVCO 1999.
Data management software.
URL: http://www.unavco.ucar.edu/software.
Last modified December 27.
Webb and Zumberge(1993)
Webb, F.H. and J.F. Zumberge 1993.
An introduction to GIPSY/OASIS-II precision software for the
analysis of data from the Global Positioning System.
JPL Publications No. D-11088. Jet Propulsion Laboratory, Pasadena,
California.
Webb, Bursik, Dixon, Farina, Marshall and
Stein
Webb, F., M. Bursik, T.H. Dixon, F. Farina, G. Marshall and R. Stein 1995.
Inflation of Long Valley caldera, California, from one year of
continuous GPS observations.
Geophys. Res. Lett. 22, 195-198.
Wessel and Smith(1991)
Wessel, P. and W.H.F. Smith 1991.
Free software helps map and display data.
EOS, Trans. Am. Geophys. Un. 72, 441 and 445-446.
Zumberge, Heflin, Jefferson, Watkins and
Webb
Zumberge, J.F., M.B. Heflin, D.C. Jefferson, M.M. Watkins and F. Webb 1997.
Precise point positioning for the efficient and robust analysis of
GPS data from large networks.
J. Geophys. Res. 102, 5005-5017.
Þorbergsson(1999)
Þorbergsson, G. 1999.
Nesjavallaveita. GPS measurements and measurements of cracks in
the Hengill area 1999 (Nesjavallaveita. GPS-mælingar og mælingar yfir
sprungur á Hengilssvæði 1999).
Skýrsla Orkustofnunar OS-99077.
Technical Report, National Energy Authority, Reykjavík
(in Icelandic).
The Icelandic continuous GPS network - ISGPS, March 18, 1999-February 20, 2000
This document was generated using the
LaTeX2HTML translator Version 98.1p1 release (March 2nd, 1998)
Copyright © 1993, 1994, 1995, 1996, 1997,
Nikos Drakos,
Computer Based Learning Unit, University of Leeds.
The command line arguments were:
latex2html -split 0 isgps.
The translation was initiated by Thora Arnadottir on 2000-06-15
Thora Arnadottir
2000-06-15